The Solar Park is performing well after its 1st week in operation
The system at the Solar Park on Manor Farm in Keinton Mandeville, Somerset is performing well after a week in operation. This week's progress included the fitting of the anchors from the PV module strings (6000 of them). The monitoring sensors were installed and the monitoring system commissioned. The plant room floor and external walls have been painted and the chequer plates were installed into the plant room trenches and earth bonded and the CCTV system was commissioned.
Next week.........
The doors to the plant room are due to be installed, the external lights and presence detectors will be installed, the performance testing will commence and the anchoring of the PV module strings will be completed.